施工钢筋加工棚是在木工加工场地、钢筋加工场地等上方有可能掉落物件或处于起重机调杆回转范围之内,应搭设双层防护棚。施工钢筋加工棚就是施工现场保护施工人员,用钢管作为支撑骨架,上面覆盖竹串片或者竹笆板或者废模板作为防砸,或者保护防护棚内经过的诸如高压线之类的东西,一般的双层防护是为了加大系数。
The construction reinforcement processing shed is above the woodworking processing site and reinforcement processing site, where objects may fall or are within the rotation range of the crane adjusting rod. A double-layer protective shed should be set up. The construction reinforcement processing shed is to protect the construction personnel at the construction site, use steel pipes as the support framework, and cover bamboo strips or bamboo fence boards or waste templates as anti smashing, or protect things such as high-voltage lines passing through the protective shed. The general double-layer protection is to increase the safety factor.
施工钢筋加工棚长和宽尺寸,要根据钢筋加工数量和使用机械的多少确定加工棚的大小,一般情况有6*9m、6*12米、9*12m等几种,可以根据实际情况酌情采用,也可自行设计长宽尺寸。
The length and width of the construction reinforcement processing shed should be determined according to the number of reinforcement processing and the number of machines used. Generally, there are 6*9m, 6*12m, 9*12m and so on, which can be adopted according to the actual situation, or the length and width can be designed by ourselves.
同时,现场钢筋加工棚一般需根据施工筹备计划,安置钢筋对焊机、切断机、弯曲机、调直机等设备的数量及加工流水线;另还需考虑部分钢筋原材料、加工后钢筋的周转及堆放;现场施工场地、用电等条件来确定;故钢筋加工棚一般跨度在12~18m,,长度尽可能大于30m。
At the same time, the reinforcement processing shed on site generally needs to arrange the number of reinforcement butt welding machines, cutting machines, bending machines, straightening machines and other equipment and processing lines according to the construction preparation plan; In addition, it is also necessary to consider the turnover and stacking of some reinforcement raw materials and processed reinforcement; On site construction site, electricity and other conditions; Therefore, the reinforcement processing shed generally has a span of 12~18m and a length of more than 30m as far as possible.
钢筋加工棚案例:
Reinforcement processing shed case:
立柱:采用150mmX150mmX3mm方钢管,中心间距4.15m,立柱焊接满焊地面预埋钢板上,立柱高3.2m,钢筋棚立柱用方钢管喷涂双色漆,底漆使用防锈漆一遍,面漆使用黄、黑两种漆,自底部刷黑漆,向上每间隔50cm交替使用黄、黑漆,共刷两遍。
Column: 150mmx150mmx3mm square steel pipe is used, with a center spacing of 4.15M. The column is fully welded to the ground embedded steel plate, and the column height is 3.2m. The column of the reinforcement shed is sprayed with two-color paint with square steel pipe, one coat of antirust paint is used for the primer, and two coats of yellow and black paint are used for the finish. Black paint is applied from the bottom, and yellow and black paint are applied alternately every 50cm upward, a total of two coats.
支架:横向采用40mmX60mmX3.5mm方钢管,跨度12m(两端各悬挑1m),与立柱焊接,支架与立柱斜撑使用40mmX60mm方钢管连接,支架与屋顶脊梁连接使用40mmX60mmX3.5mm方钢管,支架底漆使用防锈漆--遍,面漆使用铁红漆两遍。
Support: 40mmx60mmx3.5mm square steel pipe is used horizontally, with a span of 12m (1m overhanging at both ends). It is welded with the column. 40mmx60mm square steel pipe is used to connect the support with the column diagonal brace, 40mmx60mmx3.5mm square steel pipe is used to connect the support with the roof ridge, antirust paint is used for the primer of the support, and iron red paint is used for the surface paint twice.
脊梁:横向采用40mmX60mmX3.5mm方钢管,与立柱、支架焊接,并两端做悬挑,悬挑长度20cm。纵向采用C型钢50mmX80mm,共11道,刷漆两道,底漆使用防锈漆-遍,面漆使用铁红漆两遍。
Spine: 40mmx60mmx3.5mm square steel pipes are used horizontally, welded with columns and supports, and cantilever is made at both ends, with a cantilever length of 20cm. C-shaped steel 50mmx80mm is used longitudinally, a total of 11 courses, two coats of paint, one coat of antirust paint for primer and two coats of iron red paint for finish.
施工钢筋加工棚的作用及相关案例的问题就讲解完毕了,您有需求或者有问题的话可关注我们网站http://www.jnpfjc.com随时来向在线客服咨询了解。
The role of the construction reinforcement processing shed and the problems of relevant cases are explained. If you have needs or problems, you can follow our website http://www.jnpfjc.com Feel free to consult online customer service.
- 上一篇:彩钢板围挡的几种表面处理方法
- 下一篇:临边护栏生产以及安装要求详解