钢管怎么搭建木工加工棚?

来源:http://www.jnpfjc.com/   发布时间:2022-03-11

钢筋加工棚在工地是经常要用到的,那么它的搭建也是需要注意的,接下来工地钢筋加工棚就来为大家介绍一下。

The reinforcement processing shed is often used on the construction site, so its construction also needs attention. Next, the reinforcement processing shed on the construction site will be introduced to you.
钢筋加工棚采用国际标准钢材制作,在现场利用扣件将多根钢管扣接搭设成加工棚的整体式钢结构,再设置斜撑和双层防砸结构,校验钢结构强度是否符合设计要求,后在栏杆上钩挂标语横幅,整个钢筋加工棚施工完毕标准化设计。
The reinforcement processing shed is made of international standard steel. Firstly, a number of steel pipes are buckled and erected on site to form an integral steel structure of the processing shed, and then diagonal bracing and double-layer anti smashing structure are set to verify whether the strength of the steel structure meets the design requirements. Finally, a safety slogan banner is hung on the railing, and the construction of the whole reinforcement processing shed is completed with standardized design.
钢筋加工棚是施工现场内对钢筋进行拉直、弯曲、焊接等钢筋加工作业的一个场地。钢筋加工棚的长和宽,一般会根据钢筋加工数量和使用机械的多少确定加工棚的大小,一般情况有6*12m、9*12m、18*30m等几种,可以根据施工实际情况,自行设计长与宽尺寸。
The reinforcement processing shed is a place for reinforcement processing operations such as straightening, bending and welding on the construction site. The length and width of the reinforcement processing shed are generally determined according to the number of reinforcement processing and the number of machines used. Generally, there are 6 * 12M, 9 * 12M, 18 * 30m and other types. The length and width dimensions can be designed according to the actual construction situation.
钢筋加工棚工作台的布置也要合理,根据真实钢筋加工流程来,还有加工前原材料钢筋和加工结束后成品的存放,所以钢筋加工棚的地面应高于施工场地地面30cm,防止雨水浸泡,用脚手管进行搭设时,应有横杆和斜撑,以保证加工棚的稳定性。
The layout of the worktable of the reinforcement processing shed should also be reasonable. According to the real reinforcement processing process, as well as the storage of raw materials before processing and finished products after processing, the ground of the reinforcement processing shed should be 30cm higher than the ground of the construction site to prevent rainwater immersion. When erecting with scaffold pipes, there should be cross bars and diagonal braces to ensure the stability of the processing shed.
全拼装式,快速组装,拆卸简单,方便运输,型材及配件规格可按需求来定制。同时地面也需要硬化,立柱基础浇筑700*700*700mm混凝土,预埋300*300*12mm钢板。
Fully assembled, quick assembly, simple disassembly and convenient transportation. The specifications of profiles and accessories can be customized according to demand. At the same time, the ground also needs to be hardened. The column foundation is poured with 700 * 700 * 700mm concrete and embedded with 300 * 300 * 12mm steel plate.
1、施工现场所有钢筋加工场均需设置加工棚,所有露天放置的施工设备均应搭设防护棚,如搅拌机、砂浆机、输送泵:在建筑物坠落半径内或塔吊覆盖范围内的加工棚需 要设置双层防护;
1. All reinforcement processing yards on the construction site shall be provided with processing sheds, and all construction equipment placed in the open air shall be provided with safety protection sheds, such as mixers, mortar machines and transfer pumps: the processing sheds within the falling radius of buildings or within the coverage of tower cranes shall be provided with double-layer protection;
2、室外加工棚、防护棚搭设要满足规范和使用要求,四周悬挂警示标语和宣传标语(蓝底白字),地面做硬化处理;
2. The erection of outdoor processing shed and protective shed shall meet the specifications and use requirements. Safety warning slogans and publicity slogans (white words on blue background) shall be hung around, and the ground shall be hardened;
3、加工棚立柱采用方钢或圆钢制作,刷建工蓝油漆,防护棚两侧应设置八字撑,并满挂密目网,所有水平杆控制伸出立杆外侧100mm;
3. The column of the processing shed shall be made of square steel or round steel and painted with construction blue paint. Eight shaped supports shall be set on both sides of the protective shed, and a dense mesh safety net shall be hung. All horizontal rods shall extend 100mm outside the vertical rod;
4、基础采C20素砍基础(地基承载力不能满足要求时需配置钢筋),加工棚立柱与基 础预埋件可采用螺栓连接或焊接连接;
4. C20 plain cut foundation shall be adopted for the foundation (reinforcement shall be provided when the bearing capacity of the foundation cannot meet the requirements), and the column of the processing shed and the embedded parts of the foundation can be connected by bolts or welding;
5、屋盖采用镀锌铁皮瓦,刷建工蓝油漆;
5. The roof adopts galvanized iron sheet tile and is painted with construction blue paint;
6、防护棚两头进出口处张挂警示标志牌和宣传标语。
6. Safety warning signs and safety propaganda slogans shall be hung at the entrance and exit of both ends of the protective shed.
木工加工棚之工地钢筋加工棚搭建方案就介绍到这里了。希望对大家有所帮助。在工地钢筋加工棚搭建的过程中可以关注一下。不得在施工棚架上架设施工现场的临时电力线。安装和拆除避难所时,应在地面上设置围栏和警告标志,并指派专人进行监视。
The construction scheme of woodworking processing shed and site reinforcement processing shed is introduced here. I hope it will help you. You can pay attention to the process of building the reinforcement processing shed on the construction site. Temporary power lines on the construction site shall not be erected on the construction scaffold. When installing and removing shelters, fences and warning signs shall be set on the ground, and special personnel shall be assigned to monitor.